Phase II of Xinye Energy Chemical BDO strives to deliver civil engineering and safety in September

113,817
July 6, 2023, 11:28 AM
Machines roared and welding flowers flashed, and more than 300 builders chased the construction period under the scorching sun. As of now, all key basic projects of the second phase of the BDO (1,4-butanediol) project of Xinjiang Xinye Energy and Chemical Co., Ltd. have been completed, and we are making every effort towards achieving the goal of civil engineering delivery and installation in mid-September.
On July 3, workers were stepping up construction at the construction site of the BDO (1,4-butanediol) Phase II project of Xinjiang Xinye Energy and Chemical Co., Ltd.
The second phase of the Xinye Energy Chemical BDO project is located in Wujiaqu City with a total investment of 2 billion yuan. The project will build 140,000 tons of BDO, which will start in February and is expected to be completed and put into operation in August next year. The project includes the construction of BDO units, acetylene units, formaldehyde units, calcium carbide storage, transportation and crushing, and process outer pipes and pipe corridors, roads, connection with the original systems and the transformation required for connection.
BDO is a widely used chemical raw material and is widely used in textiles, plastics, medicine and other fields. Xinye Energy utilizes local superior lime, electricity, coal and other resources to produce BDO using acetylenic aldehyde process technology, which has the advantages of long continuous production cycle and good product quality. After all the second phase projects reach production capacity, they will achieve an annual output value of 2.2 billion yuan and provide more than 100 jobs.
"It is expected that all underground projects will be completed by the end of the month, 90% of the overall design of the project has been completed, and 90% of the purchase volume of process equipment has reached." Cao Lei, the person in charge of the project site, said that more than ten key basic projects of the project have been completed, and some key equipment has entered the manufacturing period. This year, we strive to complete more than 85% of the total amount of process pipelines and equipment installation.
Ma Jinrong, Secretary of the Party Committee and Chairman of Xinye Energy Chemical Corporation, introduced that in order to complete the construction of the project on schedule with high quality and quantity, a special project construction team has been established, with 6 professional groups including safety and environmental protection, civil engineering, and technology. Select business backbones to comprehensively carry out project construction and management work such as design, safety, quality, progress and cost control to ensure the smooth start-up and production of the project.
"Coordinate all participating units to organically combine design, procurement and construction to produce efficient chemical reactions to ensure that the project achieves the civil engineering and safety goals on September 15." He Suhua, deputy general manager of China Chemical Engineering No. 13 Construction Co., Ltd., the general contractor of the project, said.
It is reported that the first phase of the Xinye Energy Chemical BDO project will build 60,000 tons of BDO and will be completed and put into operation in 2019. Source: Tianshan.com