Jieyang Dananhai Petrochemical's propane dehydrogenation project started

111,155
July 5, 2023, 2:45 PM
On the morning of June 28, the concentrated start-up activities for key projects in the second quarter of 2023 in Jieyang Danhai Petrochemical Industrial Zone were grandly held at the site of the high-end new materials project of C4-C5 in Isco, Guangdong. It is reported that the five started projects cover new materials in the middle and lower reaches of petrochemical industry, fine chemicals, and basic supporting projects in the park, which will further promote the development of industrial clusters and accelerate the creation of a world-class refining and chemical industry base.
It is reported that the five projects under construction in the Dananhai Petrochemical Industrial Zone in the second quarter of this year are planned to have a total investment of 13.432 billion yuan, an estimated annual output value of 18.51 billion yuan, an annual tax payment of 1.066 billion yuan, and a land area of 1321 acres. They are Guangdong Isco Carbon Four Carbon Five Systems High-end New Material Project, Juzhengyuan (Jieyang) New Material Base Project, Jieyang Pugong New Energy LPG Storage and Distribution Warehouse-Storage, Filling and Pipeline Transportation Project, Guangdong Yumei's 100,000-ton/year energy-saving and environmentally friendly powder coating special polyester resin project, Jieyang Dananhai Petrochemical Industrial Zone Industrial Supporting Base Project.
Among them, the Juzhengyuan (Jieyang) New Materials Base project will build a 600,000-ton/year propane dehydrogenation unit and a 150,000-ton/year EVA unit.
project information
On September 2, 2022, the environmental impact report of Juzhengyuan (Jieyang) New Materials Base Project was accepted and publicized. The construction unit was Jieyang Juzhengyuan Technology Co., Ltd., which Juzhengyuan holds. The total investment of the project is 15.6 billion yuan and the construction of 600,000 tons of PDH and downstream acrylic acid esters, EVA, PP and other devices.
basic information
Construction project name: Juzhengyuan (Jieyang) New Materials Base Project
Construction unit: Jieyang Juzhengyuan Technology Co., Ltd.
Nature of construction: New construction project
Construction location: Dananhai Petrochemical Industrial Zone, Jieyang City
Investment scale: The total investment is about 15.6 billion yuan, of which environmental protection investment is 124.2 million yuan, accounting for about 0.8%.
Main equipment: The main units of this project include a 600,000 tons/year propane dehydrogenation unit, a 300,000 tons/year polypropylene unit, a 160,000 tons/year acrylic acid and a 200,000 tons/year butyl acrylate unit, a 300,000 tons/year butyl octanol unit, a 150,000 tons/year EVA unit, a 600,000 tons/year acetic acid and ester unit, a 300,000 tons/year vinyl acetate unit, A 760,000-ton/year syngas cryogenic separation unit (including a 5,000-ton/year PSA hydrogen extractor) and two 175t/h tail gas recovery units.
Construction scale: The project has an annual output of 300,000 tons/year of polypropylene products, 41,900 tons/year of acrylic acid products, 200,000 tons/year of butyl acrylate products, 30,800 tons/year of n-butanol products, 150,000 tons/year of isooctyl alcohol products, 388,800 tons/year of acetic acid products, 150,000 tons/year of EVA products, 270,000 tons/year of vinyl acetate products, 20,000 tons/year of butyl acetate products, and 31,700 tons/year of isobutyraldehyde products. The total area is 83.86hm2 and the construction area is 350427 square meters. Source: Sinochem New Network