New 15 million tons/year coal chemical project in Xinjiang is submitted for approval

115,541
June 8, 2023, 11:31 AM

Xinjiang Huineng Coal Clean and Efficient Utilization Co., Ltd. is a wholly-owned subsidiary of Beijing Longcheng Huineng Technology Co., Ltd., which is affiliated to Henan Longcheng Group Co., Ltd. and was registered and established in Yiwu County, Hami City, Xinjiang in May 2021. Xinjiang Huineng Coal Clean and Efficient Utilization Co., Ltd. plans to build a 15 million tons/year coal clean and efficient utilization project in Naomaohu Coal Mine Area, Hami, Xinjiang. The project adopts Longcheng low-temperature low-rank coal pyrolysis rotating bed (i.e., coal decomposition equipment) independently developed by Henan Longcheng Group, clean and efficient comprehensive utilization technology (hereinafter referred to as rotating bed technology). In addition to producing upgraded coal, it also processes the generated coal decomposition gas to obtain coal tar and hydrogen and simultaneously co-produce LNG, LPG, condensate and sulfur. Through hydrogenation of coal tar, naphtha, light coal tar 1 #, and hydrogenated tail oil are produced, and the naphtha is further processed through the coal-based distillate oil dehydrogenation unit to produce benzene and C7+ distillate oil.


Xinjiang Huineng Coal Clean and Efficient Utilization Co., Ltd. 15 million tons/year coal clean and efficient utilization project


Nature of construction: New construction project


Construction unit: Xinjiang Huineng Coal Clean and Efficient Utilization Co., Ltd.


Industry category and code:252 Coal processing


Construction scale:


It processes 15 million tons of raw coal every year. The project uses a 15 million tons/year pulverized coal pyrolysis unit to produce raw coal into upgraded coal, crude gas, and coal tar; among them, the crude gas produces LNG, LPG, chemical light oil and other products through a by-product LNG unit of gas hydrogen production; Coal tar is produced through a 1.5 million tons/year coal tar hydrogenation complex unit to produce light coal tar 1 #and light coal tar 2 #, and then the light coal tar 2 #and purchased naphtha are produced through a 400,000 tons/year coal-based distillate dehydrogenation unit to produce pure benzene, C7+ distillate oil and other products.


Construction location: The site is located in Baishi Lake Coal Efficient Comprehensive Utilization Industrial Zone, Yiwu Industrial Park


Project investment: The total investment is 8.85886 million yuan, and the environmental protection investment is 355.5 million yuan


Labor quota: The labor quota is 1155, including 1060 production workers and 95 technical management personnel.


Production system: 333 working days throughout the year, and 8000 hours of annual operation


Construction content:


The construction includes a 15 million tons/year pulverized coal pyrolysis unit, a comprehensive utilization of coal decomposition gas to produce hydrogen production by-product LNG unit, a 1.5 million tons/year coal tar lightweight combined unit and other projects, and corresponding public auxiliary facilities are simultaneously constructed: finished oil tank area, coal tar tank area, naphtha tank area, sewage tank area, benzene tank area, liquid ammonia tank area, liquefied gas tank area, etc.; torch facility; Water supply and fire water pressurization stations, circulating water fields, sewage treatment facilities, foam stations, accident water monitoring facilities, rainwater monitoring facilities, general substation, several regional substation, desalinated water stations, air compressor stations, air separation stations, etc.